Project Info
- Construction Date: June 2019 to November 2019
- Location: North Kingstown RI
- Category: Bridge Reconstruction, Retaining Walls
Project Details
In January 2019 NSI constructed four 40’ retaining walls at each corner of an obsolete highway bridge. The walls permitted the adjacent construction of the new bridge deck for each lane. In the Fast Bridge Program the new deck is slid into place once the old bridge lane is demolished and removed. The remove/replace sequence occurred over 48hrs in a weekend for each lane.